As part of the Hambantota Sea Port Development Project, three berths are to be constructed inside the Karagan Lawaya Lagoon. Phase-I includes the construction of quays; the construction of the cofferdam between two sets of berths; and the dredging of the lagoon in the Basin and Channel area.

Client
Sri Lanka Ports Authority
Date / Period
November 2006 to January 2007
Scope / Work Done
19 nos of boreholes drilled on and off-shore and covered quay, basin, and channel areas.
Gallery